Background

GSL successfully tendered for phase 3 of the upgrade central heating’s at Hood Manor Warrington. Our planning team provided program of works for all tenants the works included electrical periodic 
inspections, renew heating system including all pipework and radiators and boxing in all exposed pipework. We completed the program with new EPC’s for clients housing stock.

Results

All works were completed to a high standard and 6 weeks before schedule, based on the results we were awarded phase 4 of the heating upgrades.

Customer Testimonial: 

Mark Myers “Asset Manager”

“GSL Contracting have carried out planned heating replacement programme, the contractor took the lead in collaborative team working, thus creating significant savings in time. Approach to workmanship and quality was a “right first time”, with no issues or concerns with H&S throughout the project.   They were very professional, solution focused and delivered an excellent standard of work.”

Mark Myers